IEEE P802.11 - TASK GROUP Y -
MEETING UPDATE:
Status of Project IEEE 802.11y
Contention Based Protocol
Objective
Create an Amendment for the U.S.
3650-3700 MHz Broadband Wireless Services allocation (FCC 05-56)
November 6, 2008 - IEEE 802.11y-2008 is published
July 2008
11-08/0735r0, D11 comment spreadsheet
11-08/0481r2 ExCom Report
Progress
802.11y received approval to go to RevCom. 802.11y held an initial
Sponsor Ballot and four recirculation ballots. The fourth recirculation ballot
met the requirements for recirculation, and RevCom will consider D11.0 on
September 25th.
Plans for August-September 2008
The plans for August-September are to respond to comments by RevCom
and the Standards Board.
May 2008
11-08/0467r2, D10 comment spreadsheet
11-08/0480r1 RevCom Report
Progress
802.11y received conditional approval to complete Sponsor Ballot.
802.11y held an initial Sponsor Ballot and three recirculation ballots. The third
recirculation ballot met the requirements for recirculation, and RevCom will
consider D10.0 on June 11th.
Plans for May-June 2008
The plans for May-June are to respond to comments by RevCom and the
Standards Board.
Teleconference Goals
The group asked to plan for weekly teleconferences, but no
teleconference while in recirculation ballot. The next teleconference (and
maybe the only one) is 03 June, 13:00 ET. The goal of the Comment Resolution
Committee is to resolve comments.
April 2008
11-08/0443r3, D9 comment spreadsheet
11-08/0447r0, 1 April teleconference minutes
Progress
802.11y received conditional approval to complete Sponsor Ballot.
802.11y held an initial Sponsor Ballot and two recirculation ballots. The third
recirculation ballot started 3 April, and will close 18 April.
Plans for May 2008
The plans for May are to achieve the requirements to go to RevCom.
Teleconference Goals
The group asked to plan for weekly teleconferences, but no
teleconference while in recirculation ballot. The next teleconference (and
maybe the only one) is 22 April, 13:00 ET. The goal of the Comment Resolution
Committee is to resolve comments and recirculate Draft 802.11y until the
requirements are satisfied
March 2008
11-08/0318r2, meeting slides
11-08/0387r0, closing report
11-08/0359r0, meeting minutes, or latest revision
Goals for March 2008:
Objectives for the March meeting were:
- Get
WG and ExCom conditional approval to publish
Progress
802.11y received conditional approval to complete Sponsor Ballot.
802.11y held an initial Sponsor Ballot and two recirculation ballots. The next
recirculation ballot will likely occur after the 1 April teleconference.
Plans for May 2008
The plans for May are to achieve the requirements to go to RevCom.
Teleconference Goals
The group asked to plan for weekly teleconferences starting April 1st,
but no teleconference while in recirculation ballot. The goal of the Comment
Resolution Committee is to resolve comments and recirculate Draft 802.11y until
the requirements are satisfied.
January 2008
11-08/0080r1, meeting slides
11-08/0123r1, closing report
11-08/0099r0, meeting minutes, or latest revision
Goals for Jan 2008:
Objectives for the Jan meeting were:
- Prepare
the logistics for Sponsor Ballot comment resolution
Progress
LB116 closed with 271 affirmative/2 negative/54 abstention votes
(99.25% approval). TGy met for 2 regular hours during the week. We approved
minutes for Atlanta and teleconference.
Plans for March 2008
The plans for March are to ask ExCom for conditional approval to go
to RevCom.
Teleconference Goals
The group asked to plan for weekly teleconferences starting Feb 5th.
November 2007
11-07/2752r3, meeting slides
11-07/2752r2, closing report
11-07/2827r1, meeting minutes, or latest revision
11-07/2623r5, most recent comment resolution spreadsheet
Goals for Nov 2007:
Objectives for the Nov meeting were:
- Resolve all LB112 comments and create new draft
- Motion to recommend the draft 6.0 be forwarded to
Recirculation Letter Ballot (was approved 71-0-3)
3. Motion to recirculate draft 6.0 should it pass (was
approved 69-0-3)
Progress
LB112 closed
with 257 affitmative/11 negative/59 abstention votes (95.5% approval). TGy met
for 4 regular hours during the week. Tuesday we approved minutes for San Francisco, Waikoloa
and teleconferences, and comment spreadsheet 07/2623r4 and accompanying
submissions, and discussed D5.1
Thursday afternoon we created and accepted draft 5.2 and comment spreadsheet
07/2623r5 as resolving all comments from LB112, and asked the Working Group to
approve going to recirculation letter ballot, which it did on Friday 71-0-3.
The 802 ExCom
conditionally approved going to Sponsor Ballot (07/2733r0) under Procedure 19
(15-0-0).
Plans for January 2008
The plans for January
are to be in Sponsor Ballot.
Teleconference Goals
The group asked to plan for biweekly
teleconferences starting Nov 27th. An additional ninety minute teleconference
on March 11th 13:00 ET was approved. Be aware of notices on the
reflector because these may be cancelled - no need for telecons while in
recirculation Letter Ballot.
September 2007
11-07/2464r2, meeting slides
11-07/2580r1, closing
report
11-07/2505r0, meeting minutes, or latest revision
11-07/2333r6,
most recent comment resolution spreadsheet
Goals for Sept 2007:
Objectives for the Sept meeting were:
- Resolve all LB109 comments and create
new draft
- Motion to recommend the draft 5.0 be
forwarded to Recirculation Letter Ballot (was approved
42-0-2)
3. Motion to recirculate draft 5.0 should it pass (was
approved 42-0-1)
Progress
LB109 closed with 250 affitmative/17 negative/60 abstention votes (93.63%
approval). TGy met for 4 regular hours during the week. Tuesday we approved
minutes for San
Francisco and teleconferences, and comment spreadsheet
07/2333r5 and accompanying submissions, and discussed D4.1
Thursday
afternoon we created and accepted draft 4.2 and comment spreadsheet 07/2333r6 as
resolving all comments from LB109, and asked the Working Group to approve going
to recirculation letter ballot, which it did on Friday 42-0-2.
Plans for
November
The plans for November are to be in Sponsor Ballot.
Teleconference Goals
The group asked to plan for biweekly teleconferences starting July 31. An
additional ninety minute teleconference on October 30th 13:00 ET was
approved. Be aware of notices on the reflector because these may be cancelled -
no need for telecons while in recirculation Letter
Ballot.
July 2007
11-07/2143r3, meeting slides
11-07/2263r1, closing report
11-07/2269r0, meeting minutes, or latest revision
11-07/2019r6, most recent comment resolution spreadsheet
11-07/2208r2, Conditional Sponsor Ballot
Report
Goals for July 2007:
Objectives for the July meeting were:
- Resolve
all LB106 comments and create new draft
- Motion
to recommend the draft 4.0 be forwarded to Recirculation Letter
Ballot (was approved 68-0-3)
3. Prepare ExCom Procedure 20 package for Conditional
Approval to start Sponsor Ballot (was approved 15-0-0)
Progress
TGy met for 4
regular hours during the week. Tuesday we approved minutes for Orlando,
Montreal and
teleconferences, and comment spreadsheet 07/2019r5 and accompanying
submissions, and discussed D3.1
Thursday afternoon we created and accepted draft 3.2 and comment spreadsheet
07/2019r6 as resolving all comments from LB106, and asked the Working Group to
approve going to recirculation letter ballot, which it did on Friday 68-0-3.
Plans for September
The plans for
September are to resolve recirculation Letter Ballot comments, and initiate
Sponsor Ballot.
Teleconference Goals
The group asked to plan for biweekly
teleconferences starting July 31, however the recirculation letter ballot may
be delayed. Be aware of notices on the reflector because these may be cancelled
- no need for telecons while in recirculation Letter Ballot.
May 2007
11-07/0679r4,
meeting slides
11-07/0821r0, closing report
11-07/0782r0, meeting minutes, or latest
revision
11-07/0602r4, most recent comment resolution
spreadsheet
Goals for May 2007:
Objectives for the May meeting were:
- Resolve all LB104 comments and
create new draft
- Motion to recommend the draft
3.0 be forwarded to Recirculation Letter Ballot
Objectives toward July meeting
are:
1.
Recirculation LB on draft 3.0
2. Resolve all new comments
3. Establish remaining valid technical
comments
4. Prepare ExCom Procedure 20 package for Conditional
Approval to start Sponsor Ballot
Mar 2007
11-07/0392r2, meeting slides
11-07/0487r1, closing report
11-07/0395r0, meeting minutes, or latest revision
11-07/0008r12, most recent comment resolution spreadsheet
Goals for March 2007:
Objectives for the March meeting were:
- Resolve all LB94 comments and create new draft
- Hear presentations from 802.16h and host discussion
- Motion to recommend the draft be forwarded to Recirculation Letter Ballot
Progress
TGy met for 8 regular hours during
the week. Monday we approved minutes for Dallas, London and
teleconferences, and comment spreadsheet 07/0008r10 and accompanying
submissions, and discussed D1.1
Tuesday we discussed the CCA-ED and other clause 17 changes, and heard presentations form 802.16h.
Thursday we heard RTS long slot time presentation, and by straw poll of
5-1 asked for more analysis. Thursday afternoon we accepted draft 1.2
and comment spreadsheet 07/0008r12 as resolving all comments from LB94,
and asked the Working Group to approve going to recirculation letter
ballot, which it did on Friday.
Plans for May
The plans for May are to resolve recirculation Letter Ballot comments.
Teleconference Goals
The group asked to plan for
biweekly teleconferences starting March 27, however the recirculation
letter ballot may be delayed. Be aware of notices on the reflector
because these may be cancelled - no need for telecons while in
recirculation Letter Ballot.
Jan 2007
We continue bi-weekly teleconferences (January 30th
forward to February 29th, and an additional one March 6th), to process
comments from all with the goal to recirculate out of the March
plenary. 07/0098r3 is the Chair's Report and 07/0121r0 are the minutes
from London.
The teleconference schedule is bi-weekly Tuesdays, 13:00 ET and primary topics are:
- Jan 30 1 hour Clauses 3-4-5-6-9.8 (108 comments) Operating and Definitions
- Feb 13 1.5 hours Clauses 7-9.2-10-11 (327 comments) Procedures and Formats
- Feb 27 2.0 Hours Clauses 17-A-D-I-J (169 comments) OFDM PHY, PICs, MIBs, Annexes I and J
- Mar 6 3.0 hours All comment resolution contributions, plan schedule for Orlando.
Nov 2006
We continue bi-weekly teleconferences (December 5th forward to January
9th, resuming Jan 30th), and are conducting a 30-day Working Group
Letter Ballot of D1.0, to close late December, and process comments
from all to improve the quality of the draft. 06/1675r2 is the Chair's
Report and 06/1871r0 are the minutes from Dallas.
The last telecon will take place March 20th, the week after the Orlando plenary.
Sept 2006
We continue bi-weekly teleconferences (August 15th forward to November
7th), and are conducting a Working Group Technical Review of D0.01, the
review to close October 22, and process comments from all to improve
the quality of the draft. 06/1466r2 is the Chair's Report and 05/1537r0
are the Melbourne minutes.
The last telecon will take place Nov 21st, the week after the Dallas plenary.
July 2006
At the San Diego Plenary, TGy had a presentation of document number 11-06-1023r0,
and discussed PHY issues (Channelization & CCA/ED) from document 11-06/855r3.
Document 11-06/0855r3 was accepted as a starting point for normative text that,
when approved, could form Draft 0.01. The group also discussed 11-06-0955r0,1,2
(Clear Channel Assessment and Energy Detect), 11-06-0864r2, and 11-06-0867r2.
June/July 2006
We voted to adopt the Purpose, Principles and Outcome in 11-06/668r1, and are asking
for submissions about components of the initial draft. 11-06/855 and 11-06/864 have
been discussed in teleconferences, and an overview presentation will be given July
18th. Bi-weekly teleconferences beginning August 3rd to discuss the components of
the initial draft P802.11y D0.01.
April/May 2006
Bi-weekly teleconferences beginning April 19th will discuss the
situation at the FCC and changes to the candidate Requirements and
Objectives (802.11-05-1039r3).
March 2006
802.11 TGy approved March 16, 2006. 802.11-06/0412r2 is the CBP-SG
Denver Closing Report, and has SG document references.
January 2006
802.11-06/0066r1 is Waikoloa Closing Report, and has SG document
references. Bi-weekly teleconferences beginning February 1st will
discuss the situation at the FCC and changes to the candidate
Requirements and Objectives (802.11-05-1039r3).
September 2005
802.11-05/919r1 is Garden Grove Closing Report, and has SG document
references.
Bi-weekly teleconferences beginning October 19th will discuss the
situation at the FCC and changes to the draft PAR (802.11-05/565r3) and
Five Criteria draft (802.11-05-351r4).
July 2005
802.11-05/751r2 is San Francisco Closing Report, and has SG document
references.
Bi-weekly teleconferences beginning August 24th will discuss the
situation at the FCC and changes to the draft PAR (802.11-05/565r1) and
Five Criteria draft (802.11-05-351r4).
USEFUL LINKS TO OTHER SITES:
IEEE P802.11 WLANs RELATED
OTHER SITES
This page is maintained by Peter Ecclesine.
Comments
are welcome.
Copyright (c),
the Institute of Electrical and Electronics Engineers,
Inc. (IEEE).
All rights reserved.
This website may contain names, logos, designs, titles,
words, or phrases that may
constitute trademarks, service marks, or tradenames of the IEEE or other
entities
which may be registered in certain jurisdictions.