--- This message came from the IEEE 802.11 Chairs' Advisory Committee Reflector ---Based on the discussion and confirmation, the Timeline of TGbf is updated as below:
TGbf Timeline (Updated, marked in BLUE)
– PAR approved Sep 2020
– First TG meeting Oct 2020
– Comment Collection (D0.1)
Jan 2022àMar 2022à April 2022
Ø Initial Letter Ballot (D1.0)
Jul 2022à Sep 2022
à Nov 2022à Jan 2023
– Recirculation LB (D2.0)
Jan 2023à March 2023à July 2023– Recirculation LB (D3.0) May 2023à Nov 2023
– Recirculation LB (D4.0) July 2023 à Jan 2024
– Initial SA Ballot (D4.0) Sep 2023 à March 2024
– Final 802.11 WG approval July 2024 à Jan 2025
– 802 EC approval July 2024 à Jan 2025
– RevCom and SASB approval Sep 2024 à March 2025
Best Regards : )
Tony Xiao Han
To unsubscribe from the STDS-802-11-CAC list, click the following link: https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-CAC&A=1
To unsubscribe from the STDS-802-11-CAC list, click the following link: https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-CAC&A=1