Hi,
As per our discussion in the July 2019 plenary last week, the
following is the latest timeline for the development of our amendment:
2019/09: Third recirculation WGLB on Draft 5.0
2019/11: Seek EC approval for SA technical letter ballot
2019/11: Fourth recirculation WGLB on Draft 5.0 (i.e., unchanged draft)
2019/12: Initial SA technical letter ballot (Draft 5.0)
2020/03: First recirculation SA letter ballot (Draft 6.0)
2020/04: Second Recirculation SA Ballot (Draft 7.0)
2020/05: Third Recirculation SA Ballot (Draft 7.0 unchanged)
2020/07: Final 802.11 WG approval
2020/07: Final EC approval
2020/09: RevCom & Standards Board Final
Please note that the timeline is highly dependent on the development
of our two baseline standards/amendments: 802.11md and 802.11ax. We
would review the timeline again in the September interim.
As a separate note, the IEEE 802 Executive Committee has approved our
PAR extension request (19/0673r0), which is originally expired on
December 31, 2019. Given the approval, our PAR is extended for 2
years till December 31, 2021.
Regards,
Edward
_______________________________________________________________________________
If you wish to be removed from this reflector, do not send your request to this reflector - it will have no effect.
Instead, go to http://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-TGAY and then press the LEAVE button.
Further information can be found at: http://www.ieee802.org/11/Email_Subscribe.html
_______________________________________________________________________________