 Updated, thanksJ Best Regards : ) Tony Xiao
Han  发件人: Dongguk Lim [mailto:dongguk.lim@xxxxxxx]
 Hi Tony,
 Sorry for the repeat request.
 I updated the additional change in motion text to align with motion 25c. Please update the texts for motions 26 and 27 as following Motion 26
 
•     
Move to add the following to 11bf SFD: 
–   
The NDPA sounding defined in 11bf consists of: 
•     
The measurement is initiated by an NDP Announcement frame.
 
•     
The transmitter shall transmit an NDP SIFS after transmitting the NDP Announcement frame. 
•     
The detailed definition of the NDP Announcement frame is TBD. 
•     
The process to validate the STA(s) participation is TBD 
–   
Note : This can be applied to pre-HE STAs (i.e. not limited to HE and/or EHT STAs) Motion 27 
•     
Move to add the following to 11bf SFD 
–   
The TF sounding defined in 11bf consists of :
 
•     
A Trigger frame is used to solicit the NDP transmission(s).   
•     
The transmitter(s) shall transmit an NDP SIFS after receiving the Trigger frame. 
•     
The detailed definition of the Trigger frame is TBD. 
–   
Note : This is for HE and/or EHT STAs. Supporting other STAs are TBD. best regards Dongguk. From: Dongguk Lim [mailto:dongguk.lim@xxxxxxx]
 Hi Tony, To align with the agreed terminology in 11bf, based on the passed motion( i.e., Motion
 25C) and discussion with other members, I updated the motion texts. Please update the texts for motions 26 and 27 as following Motion 26
 
•     
Move to add the following to 11bf SFD: 
–   
The NDPA sounding procedure defined in 11bf consists of: 
•     
The measurement is initiated by an NDP Announcement frame.
 
•     
The transmitter shall transmit an NDP SIFS after transmitting the NDP Announcement frame. 
•     
The detailed definition of the NDP Announcement frame is TBD. 
•     
The process to validate the STA(s) participation is TBD 
–   
Note : This procedure can be applied to pre-HE STAs (i.e. not limited to HE and/or EHT STAs) Motion 27 
•     
Move to add the following to 11bf SFD 
–   
The TF sounding procedure defined in 11bf consists of :
 
•     
A Trigger frame is used to solicit the NDP transmission(s).   
•     
The transmitter(s) shall transmit an NDP SIFS after receiving the Trigger frame. 
•     
The detailed definition of the Trigger frame is TBD. 
–   
Note : This procedure is for HE and/or EHT STAs. Supporting other STAs are TBD. best regards Dongguk. From: Hanxiao (Tony,
 WT Lab) [mailto:tony.hanxiao@xxxxxxxxxx]
 Hello all, This is an advanced notification that TGbf will run motions
during the teleconference scheduled on 
l 
August 31   (Tuesday), 10am - 12:00pm ET 
l 
September 7   (Tuesday), 10am - 12:00pm ET   ----- Backup Please refer to the document linked below for a preliminary list of all the motions (starting from slide
49)  that will be run during the conference call:               https://mentor.ieee.org/802.11/dcn/20/11-20-1874-18-00bf-tgbf-motions-list.pptx Best Regards : ) Tony Xiao
Han  To unsubscribe from the STDS-802-11-TGBF list, click the following link:
https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-TGBF&A=1
 To unsubscribe from the STDS-802-11-TGBF list, click the following link: https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-TGBF&A=1  |