[8023-10GEPON] March meeting report
Dear Colleagues,
Minutes of the March meeting have been uploaded to the web: http://www.ieee802.org/3/av/public/2009_03/3av_0903_minutes_unapproved.pdf
At the last meeting, we have reviewed and resolved all 177 comments (171 received during balloting and 6 comments accepted from the floor). The final comment resolutions can be found here: http://www.ieee802.org/3/av/public/2009_03/3av_0903_comments_d3_0_accepted.pdf
My many thanks to the editors for relentlessly driving the comment resolution process, and to all task force participants for making it a good, productive meeting. It is very gratifying to see the task force being in consensus on almost all discussed issues.
The following is a tentative schedule until the next 802.3 interim meeting.
1) D3.1 to be posted                       Mar 26, 2009
2) 1st Recirc sponsor ballot opens         Apr 3, 2009
3) 1st Recirc sponsor ballot closes        Apr 19, 2009
4) Proposed D3.1 comment responses posted  Apr 24, 2009
5) Ballot Resolution Committee meeting     Apr 29-30, 2009
Thank you,
Glen Kramer
Chair, IEEE 802.3av "10G-EPON" Task Force
glen.kramer@xxxxxxxx