I agree to what you said and because we add the 34V in the PD for 802.3bt, it creates the potential confusion.
Yair
From: Peter Johnson [mailto:peter_johnson@xxxxxxxxx]
Sent: Thursday, June 14, 2018 4:38 PM
To: STDS-802-3-4PPOE@xxxxxxxxxxxxxxxxx
Subject: Re: [802.3_4PPOE] Summary of the missing requirements for Transients for <=30uS
EXTERNAL EMAIL
Clause 33
DOES include this text concerning transients under 30usec in the PSE section.
It is appropriate in Clause 33 as a means to convey that there are no PSE voltage output requirements.
Clause 33 does not make mention in the PD section that the PD can expect 34V during this period. That was added in clause 145, though I have no recollection
of when or why.
-------- Original Message --------
Subject: Re: [802.3_4PPOE] Summary of the missing requirements for
Transients for <=30uS
From: "Chad Jones (cmjones)"
<00000b60b3f54e8d-dmarc-request@xxxxxxxx>
Date: Wed, June 13, 2018 7:12 pm
To: STDS-802-3-4PPOE@xxxxxxxxxxxxxxxxx
I’m fine deleting this purely informative text. But it was voted in there for a reason and it will take 75% to get it out. I will be doing roll call votes on the call next week, and if necessary, 802.3 voters only
votes if I perceive block voting. You will have to work the TF to get the 75% majority on your side. If this thread is any indication, you have a lot of work to do.
Chair, IEEE P802.3bt 4PPoE Task Force
OK, so what if we delete this text
“Transients less than 30
μs in duration may cause the voltage at the PI to fall below VTran-2P.” and make clause 145 identical to clause 33? In this regard?
You are asking to state something is not specified. End of sentence. Not a different case and no place for this in our standard.
Please excuse tiping errors
😃
This is totally different case.
In clause 33 we add a text
“Transients less than 30
μs in duration may cause the voltage at the PI to fall below VTran-2P.” that was not appeared in clause 33.
The addition of it creates a valid question i.e. what to do with this piece of information?
I am asking to explicitly say what to do with it. To say “No requirements are specified for transients <30usec” is also clear statement which makes it similar to clause 33.
We can’t be worse than clause 33 in terms of clarity.
That is why I disagree with your statement “If we listed everything that wasn’t specified, we’d never finish” since I am not asking to specify new requirement. I am asking to clarify what was clear in clause 33
and now in clause 145 it is not.
Yair, we’ve be at this specification stuff for 15 years (you and I). Many, many times we have talked about how we don’t address what’s not addressed (and yes, that circular text was intentional). If we listed everything
that wasn’t specified, we’d never finish. I cannot support the addition of this statement.
Chair, IEEE P802.3bt 4PPoE Task Force
After seeing all the responses, I propose the following remedy to my comment below.
The concept is to make it similar to what we have in clause 33 which is no PSE requirements for transients below 30usec
Make the following changes:
"Transients less than 30
μs in duration may cause the voltage at the PI to fall below VTran-2P.
Requirements for Transients less than 30
μs in duration are not specified. See 145.3.8.6 for PD transient
requirements."
Other option is to delete “"Transients less than 30
μs in duration may cause the voltage at the PI to fall below VTran-2P.” however I see the value with keeping
this text but to complete explicitly the needed requirements which is in this case “no requirements are specified”.
--------------------------------------------------------------------------------------------
In clause 145 in the PD side we have clear requirements for what to do below 30usec and what to do between 30-250usec.
In the PSE side, it is only clear what to do between 30usec to 250usec.
Below 30usec the spec just giving us the info that the voltage can be lower than Vtran-2P but doesn’t
say what to do in this case.
If for example we didn’t have this text "Transients less than 30
μs in duration may cause the voltage at the PI to fall below VTran-2P” as we don’t have in clause 33, that
it will not be raising the question OK so what netx? What is the requirement from PSE in that case. Should we keep the power? Should we remove power? We don’t
care? Or It is system decision? (i.e. may or may not remove power or “no requirements are specified” ? This is the problem that I am trying to resolve.
To unsubscribe from the STDS-802-3-4PPOE list, click the following link:
https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-3-4PPOE&A=1
To unsubscribe from the STDS-802-3-4PPOE list, click the following link: https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-3-4PPOE&A=1
|