Re: [STDS-802-3-EPOC] Delay through the PHY
Hi Duane,
And yes indeed. Noting the names signed up next to the items, you can guess what contributions will be prepared for consideration at the January meeting.
Mark
From: Duane Remein [mailto:Duane.Remein@xxxxxxxxxx]
Sent: Tuesday, December 09, 2014 12:25 PM
To: Mark Laubach; STDS-802-3-EPOC@xxxxxxxxxxxxxxxxx
Cc: Duane Remein
Subject: RE: Delay through the PHY
Mark,
I believe this "TBD", while not a major issue by itself, points to a major hole in that we have not addressed 1D to 2D translation. The basic question of where to place a burst in both spectrum and time base solely on the time of arrival at the PHY is not addressed in the draft.
Best Regards,
Duane
FutureWei Technologies Inc.
duane.remein@xxxxxxxxxx<mailto:duane.remein@xxxxxxxxxx>
Director, Access R&D
919 418 4741
Raleigh, NC
From: Mark Laubach [mailto:laubach@xxxxxxxxxxxx]
Sent: Tuesday, December 09, 2014 12:33 PM
To: Duane Remein; STDS-802-3-EPOC@xxxxxxxxxxxxxxxxx<mailto:STDS-802-3-EPOC@xxxxxxxxxxxxxxxxx>
Subject: RE: Delay through the PHY
Hi Duane,
I've read Marek's email response and agree. I think we need to talk to a contribution on the topic so that we are grounded with respect to reference points as well as after the draft has filled in functional "holes". Without these, I feel there is not much merit in an ungrounded or open-ended discussion at this time.
Perhaps add or clarify this in the work items list?
Mark
From: Duane Remein [mailto:Duane.Remein@xxxxxxxxxx]
Sent: Tuesday, December 09, 2014 6:46 AM
To: STDS-802-3-EPOC@xxxxxxxxxxxxxxxxx<mailto:STDS-802-3-EPOC@xxxxxxxxxxxxxxxxx>
Subject: [STDS-802-3-EPOC] Delay through the PHY
In Cl 101 we have the following statement: "The actual delay is implementation dependent but an implementation shall maintain a combined delay variation through RS, PCS, and PMA sublayers of no more than TBD time_quantum (see 64.2.2.1) so as not to interfere with the MPCP timing and operation."
We have touched on this in a number of meetings but so far we have not had any proposals on how to fix the delay through the PHY.
Would it be beneficial to discuss this in tomorrow's call?
Best Regards,
Duane
FutureWei Technologies Inc.
duane.remein@xxxxxxxxxx<mailto:duane.remein@xxxxxxxxxx>
Director, Access R&D
919 418 4741
Raleigh, NC
________________________________
<="" p="">
________________________________________________________________________
To unsubscribe from the STDS-802-3-EPOC list, click the following link:
https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-3-EPOC&A=1