Re: [HSSG] Data Centre Cabling Lengths
Matt,
The survey covers "installed" cable, it doesn't cover patch cords and
equipment cables. The connections to a top of rack switch (or to a top
of rack patch panel) are not included. The copper PMD objective will
cover the connections that you describe and other connections that are
currently made by using "loose" cables.
I hope that's clear.
Hugh.
Matt Traverso wrote:
> Alan & Data Center Experts,
>
> When I re-read these charts, it seems to suggest that the "up to 10m"
> market is zero. Is the "interconnect" between 1RU server to "top of
> rack" switch application segment not included in this survey? Is it
> because this is a horizontal cabling survey?
>
> I don't understand. Could someone please address especially with
> regards to the Cu PMD objective?
>
>