----- Original Message ----- 
  
  
  Sent: Thursday, May 31, 2001 3:27 
PM
  Subject: RE: insuring the stability of 
  power delivery
  
  David, 
you bring up some good points, and you echo some of my 
  concerns. 
  First of all, my opinion is that 
  there are 5 different states of operation: 
  1) Discovery of 25K slope, the 
  behavior is well accepted at this point 
  
        2.8V to 10V delta of 2V min, PD is +/-5%, discovery time is xx ms, 
  etc... 
        the max allowed load cap is about 0.7uF (PSE 
  and PD) 
  2) Classification 
  
        it is optional for both PSE and PD 
  
        it is done at 15V to 20V, and from 5ma to 40ma (roughly) depending on 
  the class 
        it is done only after the discovery portion 
  for the protection of legacy devices, hazard matrix, etc... 
  
        the max allowed load cap is also probably about 0.7uF (PSE and 
  PD) 
  3) Power Ramp Up 
  
        there is some kind of UVLO with hysteresis, Yair's numbers are mostly 
  accepted 
        PSE and PD both manage the startup 
  current 
        0.5A is the max current for xx ms 
  
        the max cap load is now 50uF, higher values require PD circuitry to 
  buffer (to be defined) 
  4) Continuous Power Delivery 
  
        the load current is between 10ma and 350ma 
  
        the PD max power is 12.95W, the PSE min available power is 15.4W 
  
        the PSE puts out between 44V and 57V 
  
        I think that we need to add bandwidth of interest and spec the allowed 
  loads, e.g. cap loads 
  5) Power Ramp Down 
  
        occurs due to unplug after xx ms 
  
        occurs due to an over-current or other fault 
  
        must return to the discovery process before power can be applied 
  again 
  To start with, these states each 
  contain behavior that is unique to that state, 
the behavior is then simplified between different states if 
  possible. 
  My last email concerned only power 
  ramp up and continuous delivery, not classification. 
  I agree, I do not think that we can 
  get "perfect" stability, but we should decide on some performance 
  goals. 
We do not want a 
  compliant PD to oscillate so that the voltages and current are driven outside 
  of the proper 
bounds 
  therefore resulting in the power turning off. 
It can be difficult to design a PSE output that is stable 
  into any load, right? 
Phase 
  and gain margins are one way to define stability. 
We could devise a separate test fixture for 
  both the PSE and PD to test for compliance. 
  A purely resistive load should be 
  easy, where the min cap is close to zero. 
A large cap/res load is rather easy, except for huge cap 
  values. 
Again, large cap 
  values are possible if the PD provides the proper load to the PSE. 
  
Constant power loads (negative 
  resistance loads) with caps can be harder to control and specify, 
  
these types will account for most of 
  the loads we will have (IP phones, etc...) 
  I just want us to figure out what we 
  need to do to guarantee interoperability, otherwise, the standard 
  
may not succeed. 
  thanks, 
- Rick 
  
    -----Original Message----- 
From:   David 
    Kohl [SMTP:dkohl@xxxxxxxxxxxx] 
Sent:   Thursday, May 
    31, 2001 3:40 AM 
To:     Brooks, Rick [SC5:321:EXCH]; stds-802-3-pwrviamdi 
Subject:        Re: insuring the stability of power delivery 
    Rick, 
  
    
    Your questions are all good. 
    But I believe this over laps some what with the classification process. (Or 
    maybe I am just sensitive because of a real world situation that I have 
    seen.)
      
    Recently I have been made aware of a situation at 
    an end user site. The PD, (and I use this term loosely to put it in terms of 
    the groups discussion), equipment was specified as watt load of X watts by 
    Manufacturer A. The power engineering was done for Manufacturer B's 
    equipment. It was determined that a system of Y watts was required to hand 
    X*Z loads. (The system actually had 2*Y capacity) Yet in reality during 
    the start up phase of the system the real requirement for power delivery was 
    4*Y. 
      
    Unofficial investigation showed that indeed 
    Manufacturer A load specification was as stated, except during startup. During 
    start up  the system exhibited a large capacitive 
    characteristics. 
    And we all know that caps take time to charge, 
    and draw decreasing currents as they do charge. 
So initially they look like short circuits. In all other ways the PD 
    works very well. 
  
    Unspoken here is the reaction of the 
    end user. 
  
    This puts me firmly on the side of specifying the 
    behavior of both the PSE and the PD during the start up mode. In addition, 
    (now that I am thinking about this, I was not in St. Louis), should there be 
    some specification for startup during the classification process? (Now 
    I am getting away from the issue.) The point being that System Engineering 
    of the whole Ethernet link could possibly create a system which would run 
    perfectly once it is up. But because of the lack of power up specification 
    would not start. Modeling both the PSE and PD during start up mode would 
    prevent this from occurring.
        Another point. I fully 
    understand the engineering reasons for increasing the cap at the PD. But in 
    the above example this clearly did not help during the start up 
    phase. 
      
    So I have a couple of questions. 
  
    
    1)    Do we need perfect stability? Or is it possible that 
    some instability can be acceptable? ( I am defining stability as the change 
    in voltage or current over time.) I would guess that getting perfect 
    stability is not possible. But some low bandwidth instability would be 
    possible without impacting system performance. But where would this 
    instability begin to impact the signaling?
      
    2)    Is there a trade off between 
    instability and cap size, which will allow a minimum size cap to be 
    used? 
  
    Thank you for your input. 
  
David Kohl 
    
  
  
    
  
  
    
      ----- Original Message ----- 
From: Rick Brooks <mailto:ribrooks@xxxxxxxxxxxxxxxxxx> 
To: stds-802-3-pwrviamdi@xxxxxxxx <mailto:stds-802-3-pwrviamdi@xxxxxxxx> 
Sent: Wednesday, May 30, 2001 7:01 PM 
Subject: insuring the stability of 
      power delivery 
      Hi,
I just wanted to voice one concern that I have regarding 
      power ramp up, and continuous power modes.
I was reminded of this issue 
      when I was simulating the current limits in the PSE and PD and 
      watching
oscillations on the cable during startup. Yair's Pspice circuit 
      does not have these problems
due to the fact that there are Op-amps in the current 
      limit feedback loops (i.e. band limited). 
      
      It seems to me that we do not yet have a 
      defined and specified behavior that will insure that the DTE power will 
      be
delivered in 
      a stable way.
How do we guarantee that a PD from vendor "A" will not oscillate 
      when connected to a PSE from vendor "B"?
The PD as an electrical load 
      needs to be dominated by a capacitive reactance.
I think that we all agree, 
      but this has not yet been specified. 
      During power ramp up, either the PSE or PD 
      current limit will be in effect, so we need to specify the 
      behavior
during 
      power ramp up. 
      At the present time, what behavior is specified 
      to insure that the PSE feedback loops,
either to regulate the 
      output voltage, or to limit the current (protection circuits),
will not oscillate with the 
      longest UTP cable or the PD? 
      It seems that we need to address these issues 
      or we do not have a complete standard. 
      Some ideas:
1) specify the maximum loop 
      bandwidths of the PSE and PD loops so that any such system will 
      always
behave as 
      a lumped circuit. In other words, spec the loop bandwidth so that it is 
      about 6 to 10
times smaller than 1/lambda of the maximum length UTP 
      cable.
We do not 
      want sudden load changes to cause oscillation or ringing, for 
      instance.
Slew 
      rate helps, but it is a large signal behavior only. 
      2) specify a minimum phase margin into a 
      "standard" PD load (whatever that is) 
      3) specify a maximum gain at the UTP bandwidth 
      at the longest cable. 
      4) both the PSE and PD need to have a specified 
      behavior. 
      Any other ideas or discussion on this 
      topic?
How about 
      you power guys??? 
      thanks,
- Rick