Hi Yongho and Alfred
Thank you for the hard work to bring off this new version.
A few comments for correction are as follows:
Contents
Pg xiii: link to 8.4.1.15a is broken
Pg xvii: link to 9.18 is broken
Pg xx: “10.44dSensor-only BSS” should be changed to “10.44c.7 S1G BSS type and STA type”
8.4.2.6:
(Pg114,ln53, in Figure 8-124b) “B1B5” should be “B1 B5”
(Pg116,ln21) “is” should be “are”
10.3.5.11: (*pg350, ln58) “service type” should be “the service type”
The rest subclauses I reviewed (as shown below) are fine
4.3.13a1
8.4.1.b
8.4.1.15a
8.4.1.48
8.4.1.52
8.4.1.57
8.4.2.1
8.4.2.28
8.4.2.170s
8.5.23a.5
9.7.6.5.4
9.7.6.6
9.22.5.8
9.24
10.3.8
10.5
Best Regards,
Zander I2R, Singapore
From: Yongho Seok <yongho.seok@xxxxxxxxx>
Reply-To: Yongho Seok <yongho.seok@xxxxxxxxx> Date: Thursday, 9 October, 2014 12:35 am To: "STDS-802-11-TGAH@xxxxxxxxxxxxxxxxx" <STDS-802-11-TGAH@xxxxxxxxxxxxxxxxx> Subject: [STDS-802-11-TGAH] Draft 2.2 ready for review Hello all,
You can access TGah Draft 2.2 from a member only area. http://www.ieee802.org/11/private/Draft_Standards/11ah/Draft%20P802.11ah_D2.2.pdf
For your convenience, I have also uploaded LB203 comment spreadsheet. https://mentor.ieee.org/802.11/dcn/14/11-14-0796-10-00ah-tgah-lb203-comments-on-d2-0.xlsx
Please review TGah Draft 2.2 if your contributions were exactly implemented by our technical editor. Especially, from the spreadsheet, please check Edit Status and Edit Notes columns. The below is a review request from our technical editor.
Given that this draft incorporates changes that resulted from the resolutions of a quite a significant number of CIDs (~850 spread throughout ~90 documents) in a very short time (~10 days) it would be best if the authors could double check that their resolutions have been incorporated correctly in the draft. If possible with particular focus on those CIDs that have Edit Status of: IR, M, MR, NR.
As discussed in a last September F2F meeting, we should start an initial recirculation letter ballot in this week. So, the due date of the review feedback is 10/09 (6PM in PST). Please send your feedbacks to me and Alfred.
Thanks a lot, Yongho
IF YOU WISH to be Removed from this reflector, PLEASE DO NOT send your request to this CLOSED reflector. We use this valuable tool to communicate on the issues at hand. SELF SERVICE OPTION: Point your Browser to - http://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-S1G and then amend your subscription on the form provided. If you require removal from the reflector press the LEAVE button. Further information can be found at: http://www.ieee802.org/11/Email_Subscribe.html _______________________________________________________________________________ IF YOU WISH to be Removed from this reflector, PLEASE DO NOT send your request to this CLOSED reflector. We use this valuable tool to communicate on the issues at hand. SELF SERVICE OPTION: Point your Browser to - http://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-S1G and then amend your subscription on the form provided. If you require removal from the reflector press the LEAVE button. Further information can be found at: http://www.ieee802.org/11/Email_Subscribe.html _______________________________________________________________________________ |