All, As you all know, TGbh failed to get to D1.0 during the Atlanta session. As a result, we are off the planned timeline, and a timeline update is required. I propose the following changes. If anyone has comments/concerns, please let me know. PAR approved Feb 2021 First TG meeting Mar 2021 D0.2 CC May 2022 Initial WG Letter Ballot (D1.0) Mar 2023 -> May 2023 Recirculation LB (D2.0) Jul 2023 -> Nov 2023 (<- Note, I have added another meeting session, due to our ongoing debate about additional solution(s) beyond D0.2, I expect D1.0 comment resolution will take some time) Initial SA Ballot (D3.0) Nov 2023 -> Mar 2024 Final 802.11 WG approval Mar 2024 -> Jul 2024 802 EC approval Apr 2024 -> Jul 2024 RevCom and SASB approval Apr 2024 -> Sep 2024 Thanks. Mark To unsubscribe from the STDS-802-11-TGBH list, click the following link: https://listserv.ieee.org/cgi-bin/wa?SUBED1=STDS-802-11-TGBH&A=1 |