Dear Colleagues,

 

The minutes of the 802.3av April  Interim Meeting have been uploaded to http://www.ieee802.org/3/av/public/2009_04/3av_0904_minutes_unapproved.pdf.

 

This meeting has focused on resolving 113 comments (including 6 post-deadline comments). Final comment responses are recorded here: http://www.ieee802.org/3/av/public/2009_04/3av_0904_comments_d3_2_accepted.pdf.

 

Both the number of comments and the amount of technical changes were above the level we should have at this stage in our draft. To ensure that we adhere to our previously approved timeline, we will have an additional Interim meeting in Shanghai, P.R. China on June 8-9, 2009.

 

I would like to thank ZTE for organizing the meeting on a very short notice. We have a very nice venue and no registrations fees for this meeting.

 

All meeting details and registration forms are available here: http://grouper.ieee.org/groups/802/3/interims/shanghai_1_0609.html. Please, note that meeting registration and hotel reservation deadlines are on May 20th, but early registrations are always appreciated.

 

Here is our intended timeline in preparation for the Shanghai meeting:

 

May 6, 2009        - Preliminary draft (D3.2.1) is posted for preview

May 10, 2009      - Feedback on the preliminary draft (D3.2.1) is due

May 12, 2009      - Draft D3.3 is posted

May 15, 2009      - 2nd Recirculation Sponsor Ballot on P802.3av/D3.3 opens

May 31, 2009      - 2nd Recirculation Sponsor Ballot on P802.3av/D3.3 closes; Comments on D3.3 are due

June 4, 2009       - Proposed D3.3 comment responses are posted

June 8-9, 2009   - Comment resolution during June 802.3av Interim meeting

 

 

Best Regards,

Glen Kramer

Chair, IEEE 802.3av "10G-EPON" Task Force