Task | Date | Actual Date |
Status |
First unapproved draft 100 MBit/s Token Ring available for committee discussion | 31-Oct-97 | 31-Oct-97 | Complete |
Tutorial on HSTR at 802 Evening Session | 11-Nov-97 | 11-Nov-97 | Complete |
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802.5 Working Group | 12-Nov-97 | 13-Nov-97 | Complete |
Agreement reached on Technical Approach for 100 Mbit/s token ring | 13-Nov-97 | 13-Nov-97 | Complete |
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802 SEC | 13-Nov-97 | 13-Nov-97 | Complete |
Strawman 0.5 100 Mbit/s token ring circulated for comments | 21-Nov-97 | 27-Nov-97 | Complete |
Comment period on 100 Mbit/s Strawman closed | 31-Dec-97 | 7-Jan-98 | Complete |
Earliest approval of 3 HSTR PARs (t, u and v) by NESCOM | Dec-97 | 9-Dec-97 | Complete |
802.5 Interim meeting to resolve issues with 100 Mbit/s Strawman | 14 to 16-Jan-98 | 13 to 16-Jan-98 | Complete |
Start of 802.5t (HSTR) Draft 1 Ballot | 28-Jan-98 | 30-Jan-98 | Complete |
End of 802.5t (HSTR) Draft 1 Ballot | 08-Mar-98 | - | Complete |
IEEE Plenary meeting, Irvine CA | 09 to 13-Mar-98 | - | Complete |
Start of 802.5t (HSTR) Draft 2 Ballot | 01-Apr-98 | 30-Mar-98 | Complete |
Formation of ballot pool for LMSC ballot of 802.5t | 01-Apr-98 | 01 to 30 Jul-98 | Complete |
End of 802.5t (HSTR) Draft 2 Ballot | 10-May-98 | 10-May-98 | Complete |
Interim meeting 'ff' | 12 to 15-May-98 | - | Complete |
802.5t (HSTR) draft 2.1 pre-release | 10-Jun-98 | 10-Jun-98 | Complete |
802.5t/draft 2.1B re-circulation ballot start | 08-Jun-98 | 19-Jun-98 | Complete |
End of 802.5t/draft 2.1B Re-circulation ballot | 24-Jun-98 | 05-Jul-98 | Complete |
IEEE Plenary meeting, La Jolla CA | 6 to 10-Jul-98 | - | Complete |
Forward 802.5t (HSTR) to LMSC and ISO for balloting | 09-Jul-98 | 04-Sep-98 | Complete |
802.5v/strawman 0.2 ballot start | 17-Jul-98 | 16-Jul-98 | Complete |
802.5t/draft 2.2 re-circulation ballot start | 30-Jul-98 | 30-Jul-98 | Complete |
End of 802.5t/draft 2.2 Re-circulation ballot | 11-Aug-98 | 17-Aug-98 | Complete |
End of 802.5v/strawman 0.2 ballot | 17-Aug-98 | - | Complete |
Interim meeting 'gg' | 24 to 28-Aug-98 | - | Complete |
802.5t/draft 2.3 re-circulation ballot start | 26-Aug-98 | - | Complete |
End of 802.5t/draft 2.3 re-circulation ballot | 07-Sep-98 | - | Complete |
Submit 802.5t for LMSC ballot | 08-Sep-98 | - | Complete |
802.5t for LMSC ballot | 11-Sep to 19-Oct-98 | - | Complete |
Plenary meeting 'HH' | 9 to 13-Nov-98 | - | Complete |
Start of 802.5w (Errata) Draft 1 Ballot | 01-Dec-98 | 02-Dec-98 | Complete |
End of 802.5w (Errata) Draft 1 Ballot | 04-Jan-99 | 11-Jan-99 | Complete |
802.5t LMSC recirculation ballot | 15-Dec-98 | - | Complete |
Interim meeting 'hh' | 18 to 22-Jan-99 | - | Complete |
802.5t LMSC recirculation ballot closes | 22-Jan-99 | - | Complete |
802.5t 2nd LMSC recirculation ballot closes | 05-Mar-99 | - | Complete |
Plenary meeting 'II' | 8 to 12-Mar-99 | - | Complete |
802.5t forwarded to RevCom by 802 SEC | 11-Mar-99 | - | Complete |
802.5v/D1 starts initial committee letter ballot | 02-Apr-99 | 01-Apr-99 | Complete |
802.5w/D1.1 starts committee 15-day recirculation ballot | 02-Apr-99 | 03-Apr-99 | Complete |
802.5w/D1.1 recirculation ballot closes | 19-Apr-99 | 03-May-99 | Complete |
802.5v/D1 committee letter ballot closes | 03-May-99 | 12-May-99 | Complete |
Copenhagen interim meeting 'ii' | 10 to 12-May-99 | - | Complete |
802.5v/D1.1 starts recirculation committee letter ballot | 26-May-99 | - | Complete |
802.5v/D1.1 committee letter ballot closes | 25-Jun-99 | - | Complete |
802.5t approved by IEEE Standards Board | 26-Jun-99 | - | Conditional approval |
Montréal plenary meeting 'JJ' | 5 to 9-Jul-99 | - | Complete |
802.5v/D1.2 starts 15-day recirculation committee letter ballot | 22-Jul-99 | 23-Jul-99 | Complete |
802.5v/D1.2 committee letter ballot closes | 6-Aug-99 | 7-Aug-99 | Passed unanimously |
802.5w/D1.2 LMSC sponsor electronic letter ballot opens | 18-Aug-99 | 18-Aug-99 | Complete |
802.5w/D1.2 LMSC sponsor electronic letter ballot closes | 17-Sep-99 | 17-Sep-99 | Complete |
Hilo, Hawaii plenary meeting 'KK' | 8 to 12-Nov-99 | - | Complete |
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot opens | 09-Dec-99 | 09-Dec-99 | Complete |
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot closes | 19-Dec-99 | 19-Dec-99 | No comments |
802.5v/D1.3 LMSC sponsor electronic letter ballot opens | 15-Dec-99 | 22-Dec-99 | Complete |
802.5v/D1.3 LMSC sponsor electronic letter ballot closes | 26-Jan-2000 | 26-Jan-2000 | Complete |
802.5z/D1 starts 30-day committee letter ballot | 24-Dec-99 | 24-Dec-99 | Complete |
802.5z/D1 committee letter ballot closes | 31-Jan-2000 | 31-Jan-2000 | Complete |
802.5w Corrigenda to 802.5:1998 and Amd.1:1998 approved by the Standards Board | 30-Mar-2001 | 30-Mar-2001 | Complete |
802.5z Gigabit Token Ring standard approved by the Standards Board | 4-May-2001 | 4-May-2001 | Complete |
This project incorporates the former P802.5u.
Original PAR approved December 1997. The revised PAR was approved in June 1998.
This document has completed its 802 and LMSC balloting and has been forwarded to RevCom by the 802 Standards Executive Committee. It was conditionally approved as an IEEE standard at the Standards Board meeting on June 26th, 1999 in Boston, MA. The approval was conditional upon resolution of the patent issue impinging on the 100 Mbit/s PHYs. The conditional approval was extended until March 2000. Following resolution of the patent issue, the standard was ratified by the IEEE Standards Board on January 13th, 2000.
Following major procedural battles, this standard was finally approved by the Standards Board on May 4th, 2001. There are no known implementations.
The PAR change, from an errata supplement to a Corrigenda, was approved by the standards board on September 16th, 1999.
This document has completed its first LMSC ballot (802.5's first experience of an electronic LMSC ballot) with only editorial comments. Comment resolution took place at the November 1999 plenary meeting. The document was then sent out for a recirculation sponsor ballot under conditional approval rules. The corrigenda was approved by the standards board on March 30th, 2000.
This item was withdrawn in 2000 after no contributions were received.
The committee has voted to withdraw this PAR. The PAR withdrawl was approved by the standards board on September 16th, 1999.
A strawman draft was presented for consideration at the November 1999 meeting. The draft was adopted with modifications and sent out for ballot by the committee. Work on this item lapsed when the working group went into hibernation.