IEEE 802.5 Activities

Historical Committee Timetable

Task Date Actual
Date
Status
First unapproved draft[Secure] 100 MBit/s Token Ring available for committee discussion 31-Oct-97 31-Oct-97 Complete
Tutorial on HSTR at 802 Evening Session 11-Nov-97 11-Nov-97 Complete
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802.5 Working Group 12-Nov-97 13-Nov-97 Complete
Agreement reached on Technical Approach for 100 Mbit/s token ring 13-Nov-97 13-Nov-97 Complete
HSTR PARs (802.5t, 802.5u, 802.5v) approved by 802 SEC 13-Nov-97 13-Nov-97 Complete
Strawman 0.5[Secure] 100 Mbit/s token ring circulated for comments 21-Nov-97 27-Nov-97 Complete
Comment period on 100 Mbit/s Strawman closed 31-Dec-97 7-Jan-98 Complete
Earliest approval of 3 HSTR PARs (t, u and v) by NESCOM Dec-97 9-Dec-97 Complete
802.5 Interim meeting to resolve issues with 100 Mbit/s Strawman 14 to 16-Jan-98 13 to 16-Jan-98 Complete
Start of 802.5t (HSTR) Draft 1 [Secure] Ballot 28-Jan-98 30-Jan-98 Complete
End of 802.5t (HSTR) Draft 1 Ballot 08-Mar-98 - Complete
IEEE Plenary meeting, Irvine CA 09 to 13-Mar-98 - Complete
Start of 802.5t (HSTR) Draft 2 [Secure] Ballot 01-Apr-98 30-Mar-98 Complete
Formation of ballot pool for LMSC ballot of 802.5t 01-Apr-98 01 to 30 Jul-98 Complete
End of 802.5t (HSTR) Draft 2 Ballot 10-May-98 10-May-98 Complete
Interim meeting 'ff' 12 to 15-May-98 - Complete
802.5t (HSTR) draft 2.1 pre-release 10-Jun-98 10-Jun-98 Complete
802.5t/draft 2.1B re-circulation ballot start 08-Jun-98 19-Jun-98 Complete
End of 802.5t/draft 2.1B Re-circulation ballot 24-Jun-98 05-Jul-98 Complete
IEEE Plenary meeting, La Jolla CA 6 to 10-Jul-98 - Complete
Forward 802.5t (HSTR) to LMSC and ISO for balloting 09-Jul-98 04-Sep-98 Complete
802.5v/strawman 0.2 ballot start 17-Jul-98 16-Jul-98 Complete
802.5t/draft 2.2 re-circulation ballot start 30-Jul-98 30-Jul-98 Complete
End of 802.5t/draft 2.2 Re-circulation ballot 11-Aug-98 17-Aug-98 Complete
End of 802.5v/strawman 0.2 ballot 17-Aug-98 - Complete
Interim meeting 'gg' 24 to 28-Aug-98 - Complete
802.5t/draft 2.3 re-circulation ballot start 26-Aug-98 - Complete
End of 802.5t/draft 2.3 re-circulation ballot 07-Sep-98 - Complete
Submit 802.5t for LMSC ballot 08-Sep-98 - Complete
802.5t for LMSC ballot 11-Sep to 19-Oct-98 - Complete
Plenary meeting 'HH' 9 to 13-Nov-98 - Complete
Start of 802.5w (Errata) Draft 1 [Secure] Ballot 01-Dec-98 02-Dec-98 Complete
End of 802.5w (Errata) Draft 1 Ballot 04-Jan-99 11-Jan-99 Complete
802.5t LMSC recirculation ballot 15-Dec-98 - Complete
Interim meeting 'hh' 18 to 22-Jan-99 - Complete
802.5t LMSC recirculation ballot closes 22-Jan-99 - Complete
802.5t 2nd LMSC recirculation ballot closes 05-Mar-99 - Complete
Plenary meeting 'II' 8 to 12-Mar-99 - Complete
802.5t forwarded to RevCom by 802 SEC 11-Mar-99 - Complete
802.5v/D1 starts initial committee letter ballot 02-Apr-99 01-Apr-99 Complete
802.5w/D1.1 starts committee 15-day recirculation ballot 02-Apr-99 03-Apr-99 Complete
802.5w/D1.1 recirculation ballot closes 19-Apr-99 03-May-99 Complete
802.5v/D1 committee letter ballot closes 03-May-99 12-May-99 Complete
Copenhagen interim meeting 'ii' 10 to 12-May-99 - Complete
802.5v/D1.1 starts recirculation committee letter ballot 26-May-99 - Complete
802.5v/D1.1 committee letter ballot closes 25-Jun-99 - Complete
802.5t approved by IEEE Standards Board 26-Jun-99 - Conditional approval
Montréal plenary meeting 'JJ' 5 to 9-Jul-99 - Complete
802.5v/D1.2 starts 15-day recirculation committee letter ballot 22-Jul-99 23-Jul-99 Complete
802.5v/D1.2 committee letter ballot closes 6-Aug-99 7-Aug-99 Passed unanimously
802.5w/D1.2 LMSC sponsor electronic letter ballot opens 18-Aug-99 18-Aug-99 Complete
802.5w/D1.2 LMSC sponsor electronic letter ballot closes 17-Sep-99 17-Sep-99 Complete
Hilo, Hawaii plenary meeting 'KK' 8 to 12-Nov-99 - Complete
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot opens 09-Dec-99 09-Dec-99 Complete
802.5w/D1.3 LMSC sponsor electronic recirculation letter ballot closes 19-Dec-99 19-Dec-99 No comments
802.5v/D1.3 LMSC sponsor electronic letter ballot opens 15-Dec-99 22-Dec-99 Complete
802.5v/D1.3 LMSC sponsor electronic letter ballot closes 26-Jan-2000 26-Jan-2000 Complete
802.5z/D1 starts 30-day committee letter ballot 24-Dec-99 24-Dec-99 Complete
802.5z/D1 committee letter ballot closes 31-Jan-2000 31-Jan-2000 Complete
802.5w Corrigenda to 802.5:1998 and Amd.1:1998 approved by the Standards Board 30-Mar-2001 30-Mar-2001 Complete
802.5z Gigabit Token Ring standard approved by the Standards Board 4-May-2001 4-May-2001 Complete

Upcoming Meetings

IEEE 802.5 is in hibernation now that its major work is complete. If issues arise which require resolution the best approach is to email the former chairman or vice-chair, and in the case of a problem with the standards, to request an official clarification.

Working Groups


Copyright © by Institute of Electrical and Electronics Engineers, Inc.
Hosted by IEEE Standards, and maintained by John Messenger
If you have any comments on these pages, please address them to John. Site details.

Last modified by jmesseng, at 11:38pm on Thu, 5 Jul 2001