The changes to the first paragraph 5.2 are fairly
        consistent in spirit with our operation of Study Groups but
        require some attention - particularly on second extensions. The
        resulting text is:
        
"No formal activity shall take place after six months from
          the day of the first meeting of the Working Group or PAR Study
          Group without formal submittal of a PAR to the IEEE-SA
          Standards Board and assignment of a project number, unless a
          single extension of six months for that activity is provided
          by the Sponsor (see 5.1.2). The Sponsor shall include a
          rationale in its meeting minutes when granting the extension.
          A PAR Study Group is a subgroup of the Sponsor or Working
          Group that is responsible for evaluating whether a standard
          should be developed and, if so, to complete a PAR form for
          Sponsor consideration. Only the NesCom Administrator has the
          authority to assign project numbers (see the IEEE-SA Project
          Numbering Policy)."
        
        
        One thing I notice is the requirement to include a
          rationale for the extension in the minutes. There is usually
          something said about why the study group needs more time, but
          I'm not sure it is always recorded in the minutes. We should
          add it to the supporting material for the motion.
        
        
        When a study group has it's first meeting at the interim
          following the plenary where the study group was initially
          approved, its first extension results in roughly 6 months of
          operation. (E.g. approved in Nov of 2016, first meets in Jan
          2017 starting the 6 month clock, 1st extension approved in
          March.) "Roughly" because jitter in where meetings fall within
          the month means that the plenary ending the first extension
          may fall just beyond the 6 month line. (E.g., if the Jan 2017
          meeting was the Wireless interim, then the July plenary ends
          less than 6 months later, but a first day of meeting at the
          beginning of the IEEE 802.3 meeting is Jan 9 so 6 months would
          expire just before the plenary starts.
        
        
        We uses one extension to get 6 months (or in some cases 6
          months plus a few days) of operation and 2 extensions to get
          10 months of operation. 
        
        
        If we feel that going a few days over 6 months is an issue,
          we could avoid the issue by doing 2nd extension approvals at
          the opening EC meeting instead of at the closing EC meeting.
          Another option would be to process 2nd extensions on the EC
          teleconference - since that occurs in the month before a
          plenary, 6 months from it would always cover two plenaries.
        
        
        I'm also a little concerned about the "single extension"
          and whether we should try to move to doing one extension. Most
          of our study groups require a first extension and the first
          extension has never been turned down. I don't even recall a
          case where a study group looked at something for two months
          and then decided to abandon it, not requesting a 1st
          extension. So perhaps we should make the initial Study Group
          approval be for 6 months and allow one extension to add 6
          months. 
        
        
        Regards,
        Pat
        
        
       
      
      ----------
      This email is sent from the 802 Executive Committee email
      reflector. This list is maintained by Listserv.