Date Planned (original) |
Date Planned (revised) |
Action | Date Completed |
---|---|---|---|
2001/11/11-16 | Comment Resolution at Session #16 | 2001/11/16 | |
2001/11/16 | Approve Comment Resolutions and initiation of Working Group Letter Ballot | 2001/11/16 | |
2001/11/16 | New 802.16a PAR, merging licensed & unlicensed, sent to NesCom | 2001/11/16 | |
2001/11/30 | Issue P802.16/D1 and initiate Working Group Letter Ballot #4 | 2001/11/30 | |
2002/01/04 | Working Group Letter Ballot #4 closes | 2002/01/04 | |
2002/01/07 | Open Reply Comment Period | 2002/01/05 | |
2002/01/16 | Close Reply Comment Period; Commenters invited to develop resolutions | 2002/01/17 | |
2002/01/21-25 | P802.16/D1 Comment Resolution at Session #17 | 2002/01/21-24 | |
2002/01/24 | WG Letter Ballot #4, on P802.16/D1, declared passed, pending comment resolution and recirculation | 2002/01/24 | |
2002/02/04 | IEEE-SA NesCom approves PAR merger | 2002/02/04 | |
2002/02/05 | Request that IEEE issue Invitation to Ballot on P802.16a | 2002/02/04 | |
2002/02/08 | Issue P802.16/D2 and initiate WG Recirculation Ballot #4a | 2002/02/08 | |
2002/02/14 | IEEE-SA Standards Board approves PAR merger | 2002/02/14 | |
2002/02/15 | IEEE issues Invitation to Ballot on P802.16a | 2002/02/21 | |
2002/02/22 | 2002/02/25 | Close Working Group Recirculation Ballot #4a | 2002/02/25 |
2002/02/25 | Open Reply Comment Period | 2002/02/25 | |
2002/02/15 | P802.16/D2 offered for sale in IEEE catalog | 2002/02/26 | |
2002/03/06 | Close Reply Comment Period; Commenters invited to develop resolutions | 2002/03/07 | |
2002/03/11-15 | P802.16/D2 Comment Resolution at Session #18 | 2002/03/11-15 | |
2002/03/15 | Approve Comment Resolutions and request for Sponsor Ballot on P802.16a/D3 | 2002/03/15 | |
2002/03/15 | [withdrawn] | IEEE 802 (conditionally) approves request for Sponsor Ballot | - |
2002/04/08 | [withdrawn] | Inform 802 SEC that P802.16a conditions were met | |
2002/03/15 | 2002/03/22 | IEEE closes Invitation to Ballot on P802.16a | 2002/03/22 |
2002/03/25 | 2002/03/29 | P802.16a Sponsor Balloting Group formed | |
2002/03/25 | Issue P802.16a/D3 & initiate Working Group Confirmation Ballot #4b | 2002/03/25 | |
2002/04/04 | Close Working Group Confirmation Ballot #4b | 2002/04/04 | |
2002/04/04 | - | Request open of P802.16a/D3 Sponsor Ballot by IEEE | 2002/04/04 |
- | 2002/04/04 | Request IEEE 802 to approve (by email) initiation of Sponsor Ballot | 2002/04/04 |
- | 2002/04/12 | IEEE 802 approves initiation of Sponsor Ballot of P802.16a/D3 | |
2002/04/12 | Initiate P802.16a/D3 Sponsor Ballot | ||
2002/05/12 | Close P802.16a/D3 Sponsor Ballot | ||
2002/05/13 | Open Reply Comment Period on P802.16a/D3 comments | ||
2002/05/17 | Close Reply Comment Period on P802.16a/D3 comments | ||
2002/05/20-24 | P802.16a/D3 Comment Resolution at Session #19 | ||
2002/06/03 | Issue P802.16a/D4 & Request Sponsor Ballot Recirc | ||
2002/06/17 | Open P802.16a/D4 Sponsor Ballot Recirc | ||
2002/07/05 | Close Reply Comment Period on P802.16a/D4 comments | ||
2002/06/06 | Open P802.16a/D4 Sponsor Ballot Recirc | ||
2002/06/16 | Close P802.16a/D4 Sponsor Ballot Recirc | ||
2002/07/08-12 | P802.16a/D4 Comment Resolution at Session #20 | ||
2002/07/12 | Request to send P802.16a/D5 to RevCom | ||
2002/07/12 | Request to send P802.16a/D5 to RevCom | ||
2002/07/12 | IEEE 802 (conditionally) approves request | ||
2002/07/13-14 | Work all weekend creating P802.16a/D5 | ||
2002/07/15 | Issue P802.16a/D5 & Request Sponsor Confirmation Ballot | ||
2002/07/18 | Open P802.16a/D5 Sponsor Confirmation Ballot | ||
2002/07/28 | Close P802.16a/D5 Sponsor Confirmation Ballot | ||
2002/07/30 | Request final P802.16a/D5 recirc, if necessary | ||
2002/08/02 | Submit RevCom approval application for P802.16a/D5 | ||
2002/09/11 | RevCom approves P802.16a/D5 | ||
2002/09/12 | IEEE-SA approves P802.16a/D5 |